CASE STUDY 1 – Major Project £100M
Full Quantity Surveying Services for a
Specialist Main Contractor on a design, build and maintenance
project on a Target Cost, Partnering Contract basis.
A 5-year delivery programme, requiring the
introduction of new technology on the railway and the
installation of equipment, cabling and associated route-works.
A multi-disciplined project, delivered by
means of in-house resource and Sub-Contracts. The Sub-Contracts
were let under various forms including Partnering Target Cost,
Design and Build, Design only, Install only and the provision of
labour resources, which was managed by the in-house resource.
The project was let at circa £80M and the
final account was agreed at circa £120M.
Port Associates responsibilities included
|